Contemporary off the 1.4-million-mile Artemis 1 take a look at flight round across the moon, NASA’s Orion spacecraft arrived Dec. 30 again at Kennedy House Heart in Florida, the place technicians will offload propellants and payloads, and start eradicating inside {hardware} destined to fly again to the moon with astronauts on the subsequent Orion crew capsule in 2024.
The 9-t0n, 16.5-foot-wide (5-meter) spacecraft journeyed from U.S. Naval Base San Diego to Kennedy House Heart by highway inside a climate-controlled transport container. NASA mentioned the Orion crew module arrived at Kennedy on Dec. 30. Floor groups moved the spacecraft contained in the Multi-Payload Processing Facility for post-flight servicing.
The Orion spacecraft splashed down beneath parachutes Dec. 11 within the Pacific Ocean west of Baja California, finishing a extremely profitable demonstration mission that carried the capsule deeper into house than any spacecraft designed to hold individuals into house and return them to Earth. The mission lifted off from Kennedy House Heart on Nov. 16 aboard the primary flight of NASA’s House Launch System moon rocket, a super-heavy carry launcher that generated extra thrust at liftoff than any NASA-developed rocket in historical past.
With the Orion spacecraft again at its residence port, technicians will drain leftover hazardous propellants from the capsule and open the hatch to take away instrumented mannequins that rode to the moon and again on the Artemis 1 take a look at flight. Groups will even take away a organic science bundle from the Orion spacecraft’s pressurized cabin. Sensors on the mannequins collected knowledge on radiation, acceleration, and vibration on the 25-day mission.
And the Orion spacecraft’s warmth protect shall be eliminated for evaluation. The warmth protect is roofed in an ablative materials referred to as Avcoat, the identical thermal protector used on NASA’s Apollo command module and on an Orion take a look at flight in Earth orbit in 2014. Engineers modified the design of the warmth protect after the 2014 take a look at flight, changing a honeycomb construction with greater than 330,000 individually stuffed Avcoat cells to a block design with fewer than 200 molded segments.
A prime precedence for the bottom crew at Kennedy House Heart shall be eradicating {hardware} from the Artemis 1 spacecraft for reuse on Artemis 2, the moon program’s first flight with astronauts. Eight avionics packing containers flown and a crew seat flown on Artemis 1 shall be reused on Artemis 2.
The avionics items, which embrace inertial measurement items, GPS receivers, and phased array antennas, shall be retested to make sure they continue to be wholesome after the Artemis 1 mission. Then technicians will set up the {hardware} on the Orion crew module for Artemis 2, which is contained in the Operations and Checkout Constructing at Kennedy House Heart.

NASA determined years in the past to reuse a few of the {hardware} parts from Artemis 1 on Artemis 2 as a cost-saving measure.
The Artemis 2 mission will launch a crew of 4 astronauts on the second flight of NASA’s SLS moon rocket. The trajectory will take the four-person crew on a 10-day flight looping across the far facet of the moon and again to Earth.
NASA officers have mentioned it’s going to take about two years to organize the Artemis 2 spacecraft for launch after Artemis 1, a schedule largely pushed by harvesting and recycling {hardware} from the Orion capsule that simply returned from house.
“Proper now, we’re nonetheless taking a look at that two-year timeframe from Artemis 1 to 2,” mentioned Jim Free, affiliate administrator of NASA’s exploration programs mission directorate, in November.
Managers additionally need ample time to include classes realized from Artemis 1 into Artemis 2. The Artemis 1 mission was practically flawless, with solely a handful of comparatively minor points in the course of the practically month-long take a look at flight. Floor groups at Kennedy are additionally optimistic they will accomplish work on the Artemis 2 spacecraft quicker than they did on Artemis 1.
“We clearly need to attempt to do it faster,” Free mentioned.

Officers initially tagged 16 avionics items from Artemis 1 for reuse on Artemis 2. However after delays in launching Artemis 1, managers determined to reassign eight avionics parts from the Artemis 3 spacecraft and different future autos to the Orion capsule for Artemis 2, in response to Tonya Ladwig, Orion program supervisor at Lockheed Martin, the spacecraft’s prime contractor.
Underneath NASA’s Artemis program structure, the Artemis 3 mission would be the first flight to try a crew lunar touchdown, a purpose NASA says it might accomplish as quickly as 2025. NASA’s inspector normal has reported that the company is unlikely to satisfy that schedule because of considerations concerning the readiness of a human-rated lunar lander and new spacesuits wanted for strolling on the moon.
The Artemis 3 Orion spacecraft will dock in lunar orbit with a industrial human-rated lander derived from SpaceX’s Starship mega-rocket. The Starship will ferry the astronauts from the Orion spacecraft to the lunar floor, then again to Orion for return to Earth.
NASA hopes further Artemis missions later within the 2020s will set up a cadence of lunar flights about as soon as per 12 months. However {hardware} manufacturing and the behind-schedule development of a brand new cellular launch platform at Kennedy will doubtless forestall NASA from reaching the annual Artemis launch cadence, not less than by way of Artemis 4, in response to the company’s inspector normal.

Finally, NASA and Lockheed Martin need to reuse total Orion crew modules.
Artemis 1 flew with a flight battery and two flight harnesses harvested from the Orion spacecraft from the 2014 take a look at flight in Earth orbit. Ladwig mentioned Lockheed Martin plans to ramp up the reuse effort to incorporate some 600 elements from Artemis 2 by way of Artemis 5, and by Artemis 6, engineers intend to reuse about 5,000 Orion elements between missions.
The Lockheed Martin-built crew module and the European-made service module for Artemis 2 are present process preparations for launch at Kennedy. The crew module for Artemis 2 may have a number of main variations from Artemis 1, together with cockpit shows and hand controllers for the astronauts, and a full environmental management and life help system, referred to as ECLSS.
“From an Orion perspective, I might say that we’re ready for the avionics (from Artemis 1),” mentioned Howard Hu, NASA’s Orion program supervisor at Johnson House Heart in Houston. “That’s not the one principal driver for the Artemis 2 schedule. We’ve received plenty of testing of latest {hardware}. We’re placing in ECLSS and all of the crew programs. So actually a problem, however we’re doing plenty of issues very effectively as a result of we’ve accomplished it 3 times now with the crew module.”
After floor groups stack the Orion crew modules and repair modules, the spacecraft shall be stuffed with hydrazine and nitrogen tetroxide propellants, then moved to the Car Meeting Constructing for hoisting on prime of the SLS moon rocket. The core stage for the Artemis 2 moon rocket is scheduled to reach at Kennedy House Heart within the coming months from its Boeing manufacturing facility in New Orleans.
Modifications to the SLS moon rocket’s cellular launch platform will even start this spring at Kennedy House Heart, following inspections and repairs from minor harm attributable to the Artemis 1 launch.
Email the writer.
Observe Stephen Clark on Twitter: @StephenClark1.